Greenprint Partners, acting as Project Manager, seeks qualified contractors for multiple Vermont Schools Green Infrastructure Stormwater Improvements for the locations listed below. Federal Disadvantage Business Enterprise (DBE), Women-Owned, Veteran-Owned, Minority-Owned contractors and suppliers, and Small Businesses are strongly encouraged to submit a bid proposal.
Project Description: The project consists of stormwater improvements at various schools to meet the Vermont Stormwater Rules.
Locations of the work are as follows:
Bid Opening Tuesday, March 25, 2025
- Barre Town Elementary School – 70 Websterville Road, Barre, VT
- Shelburne Community School – 3435 Harbor Road, Shelburne, VT
- Albert D Lawton Intermediate School – 102 Maple Street, Essex, VT
- Harwood Union Middle and High School – 458 VT Rte 100, Moretown, VT
- Mill River Union High School – 2321 Middle Road, North Clarendon, VT
- Milton Elementary School – 42 Herrick Avenue, Milton, VT
- Rutland City Middle and Intermediate School – 71 Library Avenue, Rutland, VT
Schedule: Construction is scheduled to begin in June 2025 and be substantially completed by September 2025.
The construction work involves installing various stormwater improvements, including, but not limited to, wetland creation, underground storage facilities, disconnection areas, dry wells, storm sewers, paving, erosion control, and landscaping, depending on the location.
These projects are subject to Davis Bacon wage rates compliance and with Build America Buy America provisions.
Any interested subcontractors and suppliers should visit the following website after February 20, 2025, for information on obtaining bidding documents: www.questcdn.com under Greenprint Partners or https://www.greenprintpartners.com/resources and click on Bidding opportunities.
For additional information, please send an email to the construction project manager: Hkillian@greenprintpartners.com