The proposed route of the Champlain Parkway Credit: Graphic by John James

When officials first dreamed up Burlington’s Champlain Parkway in 1965, Lyndon B. Johnson was president, no man had set foot on the moon and Bernie Sanders was living in New York City.

The 2.3-mile stretch of road through the city’s South End is finally scheduled for construction in 2019, but a group of activists wants to halt the project and redesign it.

The Pine Street Coalition argues that the environmental review of the project is too outdated to take into account the needs of bikers, walkers and a thriving business community. The review, completed in 2010, is “stale, obsolete and invalid,” said Tony Redington, a member of the coalition who said he’s opposed the project since 2000.

The group members outlined their objections at a Tuesday press conference, where they displayed a series of detailed posters of Burlington zoning districts, maps of the project’s environmental impacts and more than 60 printed pictures showing changes to the South End since the 2010 environmental study.

The coalition also sent an inch-thick stack of papers to city, state and federal officials demanding that the federal government conduct a new environmental review. If the Federal Highway Administration or the State of Vermont doesn’t respond within 90 days, the group plans to file a lawsuit in federal court.

Burlington Mayor Miro Weinberger, for his part, isn’t having any of it.

“The time for debate, amendment and appeal has long passed,” he said in a statement. The parkway, intended to connect Interstate 189 to downtown Burlington, is expected to cost about $43 million — 95 percent of which is federal, 3 percent state and 2 percent local. 

Among the coalition members is Steve Goodkind, a former director of Burlington’s Department of Public Works, who said he oversaw the project plans for 15 years. He said the parkway would “restrict commercial development.” Another group member, Charles Simpson, was more blunt: The current design, if built, would send the city’s vibrant South End tech and art sectors into a “death spiral,” he said.

And if the project is held up for another few years — or decades? Redington shrugged. “We want to do it right,” he said.

Correction, April 5, 2018: A previous version of this story misattributed a quote to Steve Goodkind.

The original print version of this article was headlined “Endless Highway”

Katie Jickling is a Seven Days staff writer.

18 replies on “Champlain Parkway Opponents Threaten to Derail Burlington Project”

  1. Why has this project been put on hold for so long anyway? There have been many different excuses and when it finally is ready to be completed you have this other coalition that is fighting to halt it, why don’t you get a real job or fight for something worthwhile like opioid addiction, the homeless, street paving or other things that are needed!!

  2. I both live and work in that area. I enjoy going to Oakledge park, as do many people. Having a highway a few blocks away from the waterfront would be a major drag.

  3. This is the same small group of ideologues that has opposed the mall redevelopment, the City Hall park redesign, the totally misleading F-35 ballot question, and pretty much any and all development in Burlington. Somehow, this group of retirees and “artists,” who all appear to live off funds not derived from the local economy, has a monopoly on the truth on all matters related to Burlington. Enough is enough! Find another hobby. Go for a walk in the woods. Get a head start on this year’s garden. Help the homeless. March on Washington. But please, stop pretending to speak for the people of Burlington. Because you don’t.

  4. By diverting all the traffic to Lakeside Ave, then having to make a SHARP left hand turn onto Pine St, has anyone questioned how big rigs and trailers are going to be able to turn? I predict many tie ups if this 45 degree turn is kept in the project.

  5. What are the odds the completion of this project is somehow linked to the pre-sale of the mall promises Weinberger made to Sinex?

  6. //Burlington Mayor Miro Weinberger, for his part, isn’t having any of it.//

    Of course he’s not. Actually *listening* to his “constituency” (which, as of the most recent election, represents less than half of the voting public) is not within his personal charter. And, since Miro prides himself on “robust public process” that’s been proven, time and again, to already have had a pre-determined outcome, why should we expect anything different? The ability of Burlington residents to actually affect policies and decisions that impact our own lives is an illusion.

  7. I don’t know where the quote reqarding a “death spiral” came from as I have never used that phrase in reference to the Champlain Parkway. Nevertheless, this is an antiquated and outmoded design concept that is no longer favored by the transportation design community. We are asking that the FHWA adhere to it’s existing policy of requiring periodic EIS reviews to ensure that projects are still viable and incompliance with current standards. The last such review of this project was nine years ago. Such reviews typically occur every 4 to 6 years as was the case in the past with the Champlain Parkway project.

  8. 43 million is a lot of tax payers money. I come from Glasgow in Scotland originally. The west end of Glasgow was horribly scarred and divided by a massive road building project in the 70s. It impacted businesses and that part of the city never really recovered. Especially since it is just going onto Pine St anyway. Why not just do a right turn onto Pine St at the end of the high way? I don’t see any logic/advantage in this proposal, which is probably why it never got built.

  9. “Among the coalition members is Steve Goodkind, a former director of Burlington’s Department of Public Works, who said he oversaw the project plans for 15 years” – so if Goodkind was in charge for so long, why didn’t he fix it when it was his job to? The fact that he’s now involved in a lawsuit to stop this (and other things) from happening in Burlington is laughable. Maybe somebody needs to remind him that he lost the Mayor’s race a few years ago since he seems to be trying to run this city from behind what seems to be an endless number of lawsuits and protests.

Comments are closed.