City Place Burlington construction site on Tuesday Credit: Katie Jickling

When developer Don Sinex pleaded to the Burlington City Council on August 27 that he needed to get started on foundation work for the huge CityPlace Burlington project, he portrayed the situation as urgent.

The downtown site was ready for the work, Sinex told Seven Days in an email. Not moving forward would delay the project up to three months and would mean higher costs for construction, he told reporters before the council’s vote.

The council gave Sinex permission to lay the foundation of the proposed 14-story building before all the project’s funding and contracts were in place. Sinex said at the time that he planned to start the foundation work within two weeks.

Nearly six weeks later, he has not filed the paperwork to get a city permit for the foundation, according to Burlington’s Department of Public Works.

“We’re losing patience,” said Jeff Glassberg, a consultant who is monitoring the project for Burlington. The city is encouraging the developer to “move ahead,” he said.

The mixed-use development is being built where much of Burlington Town Center mall once stood. The mall was demolished earlier this summer, but the site has seen little activity since. Plans call for housing, retail and office space.

“It’s a huge project,” Glassberg acknowledged. “But I’m sorta like ‘Get at it, guys. You’re the experts.'”

Mayor Miro Weinberger, who championed the project despite opposition from citizens’ groups, said Tuesday that he has grown “concerned about the lack of progress on the site.”

“The City has made good on all of its commitments to the project,” Weinberger said in a statement to Seven Days. “It is time for the developers to act and begin site construction, and to communicate their progress to the public regularly.”

Sinex attributed the delays to a disagreement with construction manager PC Construction, which has slowed the drafting of a new contract with the South Burlington firm to oversee the next portion of the project.

“They’re up to snuff now, and they’re doing everything a guy like me expects,” he said, calling himself a “tough hombre” to work for. “It’s a question of getting all the little ducks in order.”

He said he expects to finalize the contract and seek the permits for the foundation within two weeks.

Sinex defended his work, saying that he had been “completely, 100 percent” upfront with the city.

City councilors and Glassberg said they weren’t losing faith in Sinex. After all, Glassberg said, Sinex has already made substantial progress and continues to express “full commitment to the project.”

Still, Glassberg called the situation “pretty odd.”

“It’s way too quiet over there,” he said. On Tuesday afternoon, a sole excavator dug in the soil of the huge and empty lot.

City officials say they’re in the dark about reasons for the delay. “We granted the amendment to pour the foundation and there was some controversy,” said Council President Kurt Wright (R-Ward 4). “We want to understand why he hasn’t.”

When Councilor Jane Knodell (P-Central District) was council president last year, she said Tuesday, she pushed for quarterly updates from Sinex. “We never quite got there. It’s not too late to fix that and improve that,” she said.

The project has already faced several delays. A citizen’s group filed a suit over it. Last winter, workers found asbestos in part of a roof of the old mall, slowing down the demolition process.

Both Wright and Knodell said they hope to have Sinex update the council next Monday. “We’re trying to be good working partners. Certainly, I think Don should keep us informed,” Wright said. “There is definitely a concern.”

If Sinex doesn’t draw the foundation permit by November 1, Councilor Dave Hartnett (D-North District) said he will seek to allow city residents to park in the vacant dirt lot.

“I hate to leave that area boarded up,” Hartnett said, noting that it’s better to allow holiday shoppers to make use of the space.

Katie Jickling is a Seven Days staff writer.

17 replies on “Developer Has Not Sought Foundation Permit for Massive Burlington Project”

  1. Who does Sinex sound like when he blames local construction company for delaying project? “Theyre up to snuff now, and they’re doing everything a guy like me expects,” he said, calling himself a “tough hombre” to work for.

    Tough hombre wasn’t paying the contractor. That sounds familiar too.

  2. The external factors that have control over this project do not support his–or the Mayor’s–optimistic view.

    10-year treasuries continue to rise, now yielding well above 3.2% (nearly 100 basis point rise vs year ago) and the Dow’s dropping 600 points as I type this. We’re being hit with the double-whammy of rising interest rates on a market correction of US equity prices.

    What happens on Wall Street will affect this project dramatically, and the City Council and Mayor have refused to acknowledge that. The Council dragged on the permitting process longer than they needed to, adding unnecessary requirements and doing nothing to mitigate the type of downside risk Sinex is experiencing in global financial markets.

    Hello Newport?

  3. Who is supplying the popcorn for this dog and pony show? Miro saw all the $$$ in Sinex’s eyes and fell like a ton of bricks. Now we’re left with a hole in the ground and the incredible disappearing Sinex. Figures. When all you do is hustle for corporate sponsors, you get what you deserve.

  4. Why doesn’t the city just sue Don the con and get another contractor and not one of miros friends??? That would be more reasonable then just waiting around for something to happen! City hall can be so stupid sometimes

  5. There was some funny stuff regarding the timing of that election and in how quickly Miro got it on the ballot and if I recall, during a month where voter turnout is typically lower. There were several somewhat shady dealings with the mall vote and I would definitely say Miro pushed it through.

  6. “Miro rammed this 14 story unicorn down our throats”

    A lie. The voters of Burlington voted for it. As did the city councilors who are elected by the voters of Burlington. As did the voters who re-elected Miro as Mayor.

  7. You think Newport has big hole in its downtown…..

    My experience is when you don’t have money to pay contractors they don’t work?

    Burlington has bigger issues than running there sewer and storm water together.

    It’ll take longer to complete this project than building the south end connector.

    Ship out of luck

  8. Did this delay give Sinex the time to get the funding he didn’t have and needed before Weinberger looked the other way in allowing him to start the foundation?

  9. Jane Knodell seems to be the problem to every solution. Her agenda of harming the public good for no good reason is mystifying. Is it possible to impeach a city councilor? If not, Id like to add creating that law to the agenda. The corruption or gross incompetence of her entrenched confederacy of dunces has severely harmed all residents. Jane Knodell is a blight that needs to be excised from our beautiful city.

  10. This project is built on a lie by a practiced liar and enabled by a liar in the Mayor’s office. Miro rammed this 14 story unicorn down our throats and now he has to answer for it. Of course City Council will do nothing about this except voice their “concern”.

Comments are closed.